Project

General

Profile

Startup Calibrations » History » Version 2

Amber Herold, 04/27/2010 10:41 AM

1 1 Amber Herold
h1. Startup 
2
3
4
5
6
7
h2. Microscope Setup
8
9
10
11
12
13
*  Setup normal mode configuration and deactivate the low dose kit if you have not
14
done so.
15
16
17
*  Align the scope.
18
19
20
21
22
23
24
25
26
27
h2. Run Leginon Client on the Microscope Computer
28
29
30
31
See Instruction in "Start Leginon" Chapter about "<link linkend="test_start_client">Run
32
Leginon Client on the Microscope Computer</link>"
33
34
35
36
37
38
h2. Start Leginon
39
40
41
42
See Instruction in "Start Leginon" Chapter about "<link linkend="test_start_main">Run
43
Leginon at your main working station</link>"
44
45
46
47
48
49
h2. Launch the Application
50
51
52
Leginon/Main menu/Application> select "Run...." and choose the application named
53
"Calibrations", select the microscope name as the instrument and the local computer as
54
"main", and then launch the application.
55 2 Amber Herold
56
57
______
58
59
[[Grids for Calibration|< Grids for Calibration]] | [[Creating Presets for the first time|Creating Presets for the first time >]]
60
61
______