h1. Startup 
2
3
4
5
6
7
h2. Microscope Setup
8
9
10
11
12
13 5 Amber Herold
*  Setup normal mode configuration and deactivate the low dose kit if you have not done so.
14 1 Amber Herold
15
16
*  Align the scope.
17
18
19
20
h2. Run Leginon Client on the Microscope Computer
21
22
23 3 Alex Kadokura
24 5 Amber Herold
See Instruction in "Start Leginon" Chapter about [[Run Leginon Client on the Microscope Computer|Run Leginon Client on the Microscope Computer]]
25 3 Alex Kadokura
26 1 Amber Herold
27
28
29
30
h2. Start Leginon
31
32
33
34 5 Amber Herold
See Instruction in "Start Leginon" Chapter about [[Start Leginon at your main working station remotely|Run Leginon at your main working station]]
35 4 Alex Kadokura
36 1 Amber Herold
37
38
h2. Launch the Application
39
40
41 5 Amber Herold
Leginon/Main menu/Application> select "Run...." and choose the application named "Calibrations", select the microscope name as the instrument and the local computer as "main", and then launch the application.
42 2 Amber Herold