h1. Align tilt series
2
3 10 Anke Mulder
!http://emg.nysbc.org/attachments/267/Picture_62.png!
4 5 Anke Mulder
5 3 Anke Mulder
h2. General Workflow:
6
7 18 Anke Mulder
# Select the tiltseries to align.
8 3 Anke Mulder
# Check the runname and enter a description.
9 1 Anke Mulder
# Use the radio button to select Protomo Refinement or IMOD shift-only alignment.
10 4 Anke Mulder
# To submit the job to the cluster click the "Align Tilt Series" button.  Alternatively, click on "Just Show Command" to obtain a command that can be pasted into a UNIX shell.
11 1 Anke Mulder
!http://emg.nysbc.org/attachments/263/Picture_55.png!
12 8 Anke Mulder
# If your job has been submitted to the cluster, a page will appear with a link "Check status of job", which allows tracking of the job via its log-file. This link is also accessible from the "1 running" option under the "Aliogn tilt series" submenu in the appion sidebar.
13 12 Anke Mulder
# Now click on the "1 Complete" link under the "Align tilt series" submenu. This opens a summary of all tilt series alignment runs that have been completed for this dataset.
14 1 Anke Mulder
!http://emg.nysbc.org/attachments/266/Picture_61.png!
15 12 Anke Mulder
# Clicking on the "alignrun id" opens a summary page for the alignment cycles that were run.
16 13 Anke Mulder
# Clicking on the "refine cycle" number opens a report page for that cycle including input parameters and directory paths.  Clicking on "Alignment Movie" opens a new web-browser with a movie of the aligned tilt series.
17 19 Anke Mulder
# The same alignment cycle can be repeated by clicking "Repeat Last Aligner Iteration" or another initiated by clicking "Setup Next Aligner Iteration" (See Step 11 below).
18 17 Anke Mulder
# In order to [[Create full tomogram|calculate a tomogram]] from the aligned tiltseries, click on the "Create full tomogram" link in the Tomography menu on the Appion Sidebar.
19 1 Anke Mulder
!http://emg.nysbc.org/attachments/272/Picture_70.png!
20 19 Anke Mulder
# If you selected "Setup Next Aligner Iteration" in step 9, then:
21
22 3 Anke Mulder
23
h2. Notes, Comments, and Suggestions:
24
25 2 Anke Mulder
26
______
27
28
[[Tomography|< Tomography]] | [[Create full tomogram|Create Full Tomogram >]]
29
30
______