Use the following guidelines for creating your first Appion project.
6
 
7 1 Amber Herold
8 27 Amber Herold
9 26 Amber Herold
h2. 1 Go to the main web page 
10 1 Amber Herold
11 18 Amber Herold
The url will vary based on your host name.
12 1 Amber Herold
13 18 Amber Herold
http://localhost/myamiweb/
14
15 26 Amber Herold
h2. 2 Log into myamiweb 
16 18 Amber Herold
17 35 Amber Herold
With the username "administrator" and the administrator password created in the wizard, log into myamiweb as shown below. 
18 18 Amber Herold
If you did not enable user login in the setup wizard, you will not be prompted for a password.
19
20 24 Amber Herold
___
21
22 11 Neil Voss
!default_login.png!
23
24 24 Amber Herold
___
25
26 19 Amber Herold
.
27
.
28
.
29 18 Amber Herold
You will then see the default layout for the administrator.
30 19 Amber Herold
.
31
.
32
.
33 11 Neil Voss
34 24 Amber Herold
___
35 20 Amber Herold
36 14 Neil Voss
!admin_layout.png!
37 24 Amber Herold
38
___
39 1 Amber Herold
40 2 Amber Herold
41 25 Amber Herold
h2. 3 Add yourself as a user
42 26 Amber Herold
43 25 Amber Herold
# Select the Administration application.
44
# Select Users
45
# Select Add new user
46 1 Amber Herold
# Complete the new user form
47 27 Amber Herold
# There are four default groups available. You may also [[Groups|create a new group]]. 
48 25 Amber Herold
## administrators
49 1 Amber Herold
## power users
50 25 Amber Herold
## users
51 1 Amber Herold
## guests
52 26 Amber Herold
# Click on [add].
53 1 Amber Herold
54 27 Amber Herold
More about [[Users]].
55
56 32 Anchi Cheng
h2. 4 Create a project
57 3 Amber Herold
58 27 Amber Herold
# From the start page, select the ProjectDB application.
59
# Select "Add a new project"
60 1 Amber Herold
# Complete the form
61 27 Amber Herold
# Click on [add]
62
# Click "View Projects" to see your newly created project
63
# Select your new project to view it 
64
65 34 Anchi Cheng
h2. 5 Create the processing database for the project
66 27 Amber Herold
67 34 Anchi Cheng
Follow the instructions in [[Create a Processing Database]]. This will hold all the Appion processing data for your project.
68 27 Amber Herold
69 32 Anchi Cheng
h2. 6 Upload images to a new session
70 27 Amber Herold
71 28 Amber Herold
You can download sample images from "here":http://emg.nysbc.org/projects/appion/files.
72 40 Anchi Cheng
Then follow the steps in [[Upload_Images_to_a_new_Project_Session|Upload Images]].
73 36 Amber Herold
You can use Pixel size of .83, binning of 1, magnification 100,00, high tension 120, defocus -0.89.
74 6 Amber Herold
75 32 Anchi Cheng
h2. 7 View the images
76 29 Amber Herold
77
Once your images have been uploaded to a session, you can view them in the Image Viewer application. 
78
79
# Return to ProjectDB and select your project
80
# Sessions are listed in a table, select the session that you just created.
81 7 Amber Herold
# The image viewer will open with the first image in your session displayed.
82 1 Amber Herold
83 32 Anchi Cheng
h2. 8 Process Images
84 7 Amber Herold
85 30 Amber Herold
From the image viewer, click on the [processing] button at the top of the screen. This will open the Appion processing pipeline application. 
86
From there, follow the directions in [[Process Images]] to confirm that your installation is functioning properly. 
87 8 Amber Herold
88
______
89
90 38 Amber Herold
[[Setup Remote Processing|< Setup Remote Processing]]